The Latest

Update as of October 22, 2024


Update as of October 18, 2024

  • Marin Independent Journal Publishes Mill Valley school overhaul stalls over new environmental concerns” — The article discusses the timing implications of the recent project delay due to regulatory concerns. The earliest CEQA will be complete is July 2025. The article then says that the earliest construction could start is 5-6 months later, or more, as it will take the architect several months to complete the design once CEQA is complete. Once the designs are complete, the California Division of the State Architect will need to approve, and other permits will need to be obtained. The District has not yet specified, but it looks like the move to the temporary campus may be pushed out at least another year.


Update as of October 16, 2024

  • Petition Delivered. We delivered our petition, signed by over 200 people, to the School Board, Mill Valley City Council, Department of Toxic Substances Control, Department of Education, Marin County Office of Education, State Architect, Mill Valley Citizens Bond Oversight Committee and State Geological Survey. Keep the signatures coming! We can always send another round.

  • Department of Toxic Substances Expressed Concerns. The Department of Toxic Substances Control (“DTSC”) sent the District a letter, dated July 25, 2024, reciting the site’s history as a burn dump with previous soil tests reveling “elevated concentrations of metals (copper, lead, and zinc) and total petroleum hydrocarbons.” Given this history, DTSC warned, “we recommend the District consider that a conservative remedial option may be necessary for evaluation in the EIR.” The agency also included a sobering warning that the existing school’s support piers “extend though the former landfill and deep into the bay mud, creating a preferential pathway for landfill leachate to infiltrate to groundwater,” so DTSC wants that evaluated in the Environmental Impact Report as well. 

  • Marin County Expressed Concerns About Radiation. The Marin County Environmental Health Services division also sent the District a letter, dated August 5, 2024, which advises, “Radiation monitoring should be performed as radioactive waste has been found at other burn dump sites.”

  • Project Thus Delayed. Given heightened DTSC and County Environment Health Services concerns, the project timeline was recently pushed back. At the October 10, 2024 Board meeting, the School Board presented a revised timeline that pushes the Draft EIR Public Review Period back from October 2024 to February 2025, the EIR Notice of Determination back from January 2025 to July 2025, and the start of construction back from June 2025 to September / October 2025. 

  • Unclear if it is Possible for Portable Campus to Open in Fall of 2025 as District Anticipated. Prior School Board decks showed 7 months for construction of the temporary campus. Construction of the temporary campus cannot start until the EIR is final and CEQA complete (now July 2025 at the earliest). Can the temporary campus be built in under a month to be ready for the start of school in August 2025? Will everything be pushed back a year with an actual move into portables and start on the permanent campus to February 2026? This timeline needs further clarification. Stay tuned for updates!